SUBJECT: Construction of Restrooms on the Riverwalk

INITIATED BY: Planning Department


Recommendation: Approve the resolution authorizing the City Manager to enter into an agreement with the Georgia Department of Transportation to construct needed restroom under the Martin Memorial Bridge. Item delayed March 11, 2014 agenda.

Background: There is a need for additional restrooms to serve the general public utilizing the Riverwalk and the Martin Pedestrian Bridge.

Analysis: This project will allow for the construction of a restroom facility along the Riverwalk, under the Martin Pedestrian Bridge.

Financial Considerations: Funding for this project is being provided by a Georgia Department of Transportation High Priority Project (HPP) grant. The total cost for construction is $243,861.60. Eighty percent or $195,088.80 will be paid for by the HPP funding, with the remaining twenty percent or $48,772.80 to be paid from the city's Paving Fund. In addition, the Uptown Columbus Executive Board has notified the city that it has approved a $10,000 contribution for these restrooms. This funding will be used to reduce the city's required twenty percent match to $38,772.80.

Projected Annual Fiscal Impact Statement: The restrooms will require daily routine maintenance from the Parks and Recreation Department.

Legal Considerations: None

Recommendations/ Actions: Approve the resolution authorizing the City Manager to enter into an agreement to construct needed restroom under the Martin Memorial Bridge.



0007559 - Contract.pdf14th Street Bridge Restrooms - Uptown Columbus.pdf14th Street Bridge Restrooms - Uptown Columbus.pdf


A RESOLUTION

NO. _____


A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO AN AGREEMENT WITH THE GEORGIA DEPARTMENT OF TRANSPORTATION FOR THE CONSTRUCTION OF RESTROOMS ON THE RIVERWALK.

WHEREAS, the City has expressed a need to construct restrooms on the riverwalk under the Martin Pedestrian Bridge using Georgia Department of Transportation High Priority Project (HPP) funds; and,

WHEREAS, the cost of construction for these restrooms will be $243,861.60, with $195,088.80 being paid with the HPP funds and the remaining $48,772.80 by the city as its match for this grant; and,

WHEREAS, the Uptown Columbus, Inc., Executive Board will contribute $10,000 towards this project;

NOW, THEREFORE, THE COUNCIL OF COLUMBUS, GEORGIA, HEREBY RESOLVES AS FOLLOWS:


I.

That the City Manager is hereby authorized to enter into an agreement with the Georgia Department of Transportation to accept HPP funding for the construction of restrooms on the riverwalk to be located under the Martin Pedestrian Bridge from the Paving Fund; and,

II.

That the City Manager is further authorized to accept the $10,000 financial contribution of Uptown Columbus, Inc., for this project.

___________

Introduced at a regular meeting of the Council of Columbus, Georgia, held the _________ day of _____________ 2014, and adopted at said meeting by the affirmative vote of _____________ members of said Council.


Councilor Allen voting __________.
Councilor Baker voting __________.
Councilor Barnes voting __________.
Councilor Davis voting __________.
Councilor Henderson voting __________.
Councilor Huff voting __________.
Councilor McDaniel voting __________.
Councilor Turner Pugh voting __________.
Councilor Thomas voting __________.
Councilor Woodson voting __________.

______________________________ ____________________________
Tiny B. Washington, Clerk of Council Teresa Pike Tomlinson, Mayor